In Reynoldsville, 600 linear feet of deteriorated water line will be replaced along Jackson Street between Fourth and Fifth streets.
The total estimated cost is $152,000 with $46,982 from local funds and $105,018 from CDBG money.
In Big Run, a project at the War Memorial building will make the rest rooms Americans with Disability Act compliant.
The total estimated cost is $96,000 with $10,000 from local money and $86,000 from CDBG money.
In Punxsutawney, CDBG money will cover the $81,220 cost of the Clark Terrace Street Improvement project.
Work will be done to replace a deteriorated section of retaining wall along Clark Terrace near the intersection of Graffius Ave.